The system operator has asked the Petroleum Division and SNGPL to arrange LNG cargoes early, as Pakistan LNG Limited re-tenders after rejecting bids it found too costly.
Key points
- ISMO has warned that inadequate RLNG for gas-fired power plants could create stability risks and more load management this winter.
- It named Haveli Bahadur Shah, Bhikki, Balloki and Punjab Thermal Power Limited as plants whose operation on diesel has not been stable in the past.
- Pakistan LNG Limited rejected spot bids of about USD 27.30 to USD 31 per MMBtu for December and about USD 27.10 for January, and issued a fresh tender with bids due on 18 November 2026.
- The government plans 18 LNG cargoes for November 2026 to February 2027, down from an earlier estimate of 24.
The Independent System Market Operator (ISMO) has warned that inadequate supplies of re-gasified LNG (RLNG) to gas-fired power plants could expose the electricity system to stability risks this winter, according to Business Recorder. ISMO's letter says this could potentially result in increased load management.
In a letter to the Director General (Gas) at the Petroleum Division and the Managing Director of SNGPL, ISMO Executive Director System Operation Muhammad Zakria asked for early arrangements for RLNG cargoes.
Four plants named
ISMO identified Haveli Bahadur Shah, Bhikki, Balloki and Punjab Thermal Power Limited. It said their operation on high-speed diesel has not remained stable in the past. That limits the option of switching fuel. The letter says the power system is likely to face stability risks without adequate RLNG.
Bids rejected, new tender issued
Pakistan LNG Limited (PLL) issued a tender on 4 November 2026 for two spot cargoes of 140,000 cubic metres each, with a tolerance of plus or minus five percent, for delivery at Port Qasim, Karachi. One was for 14-16 December 2026 and the other for 9-11 January 2027.
PLL received three bids from two companies. For December, TotalEnergies Gas & Power offered about USD 27.30 per MMBtu and QatarEnergy Trading quoted USD 31. For January, TotalEnergies quoted about USD 27.10. TotalEnergies was the lowest evaluated bidder for both windows. PLL did not proceed, judging the prices too high.
On 12 November it floated a new tender for the same two windows on a Delivered Ex-Ship basis. Bids are due on 18 November 2026. Business Recorder said the availability and price of cargoes remain uncertain.
Cargo target cut
The government has finalised a winter gas plan to buy 18 LNG cargoes from November 2026 to February 2027. An earlier proposal was 24. The plan is to maximise deliveries under two long-term contracts with Qatar, and to add spot or other supplies if needed. The Petroleum Division is also pursuing diplomatic engagement with Qatar.
The earlier estimate of 24 cargoes for the SNGPL network was made up of nine for the power sector and 15 for domestic consumption (9 + 15 = 24). Two further cargoes were envisaged as contingency supplies, in addition to the 24. Business Recorder said the lower target raises the importance of allocating enough fuel to power plants at peak demand.
Earlier failures
PLL also rejected spot offers in September. These were about USD 26.97 per MMBtu from BP Singapore for 4-8 September and about USD 26.71 for 8-12 September. A later tender for 12-16 September drew no bids, the paper reported.
The shortage has already affected electricity generation, with RLNG-based plants facing fuel constraints, according to Business Recorder.
Sources
- RLNG shortage to risk winter power supply, ISMO warns — Business Recorder, 17 November 2026
How this story was made
Researched and written by the Pakistan Republic AI newsroom from the sources listed above, then checked against them before publishing. Stories about people, politics, courts or crime are also reviewed by an editor.