Reko Diq cost estimate rises 30pc to $9.1 billion, ICMA report says
The Institute of Cost and Management Accountants says production could slip to 2030, raising risks for three state-owned firms that have committed about $1.88 billion.
Key points
- According to ProPakistani's account of an ICMA report, Reko Diq's estimated development cost has risen 30 per cent to $9.1 billion from $7 billion.
- Initial production could be delayed by two years to 2030, though Barrick has not formally confirmed a revised date.
- OGDCL, PPL and GHPL have committed about $1.88 billion and together own 25 per cent of the project.
- The report, as relayed by ProPakistani, warns that projected cash flow of $74 billion should not be mistaken for revenue accruing directly to Pakistan.
The estimated development cost of the Reko Diq copper-gold project has risen 30 per cent to $9.1 billion from $7 billion, according to a report by the Institute of Cost and Management Accountants (ICMA), as reported by ProPakistani. The report also says initial production could be delayed by two years to 2030. All ICMA findings in this article are as relayed by ProPakistani; the ICMA document itself was not available for review.
Cost breakdown
The Phase I investment estimate has increased from $4 billion to $5.6 billion. Phase II costs have risen from $3 billion to $3.5 billion. The project is planned around a 37-year mine life. Phase I is expected to process 45 million tonnes of ore a year, rising to 90 million tonnes in Phase II.
Exposure of state-owned firms
Oil and Gas Development Company Limited (OGDCL), Pakistan Petroleum Limited (PPL) and Government Holdings (Private) Limited (GHPL) have together committed about $1.88 billion. Together they own 25 per cent of the project. Barrick holds 50 per cent and the Government of Balochistan the remaining 25 per cent.
The report says delays could postpone dividend income, increase financing exposure and raise the opportunity cost of the committed capital.
Review and delay
According to ProPakistani, Barrick began a review of the project in February 2026 amid security concerns in Balochistan. It announced a slowdown in development in April and extended the review until mid-2027 to reassess security, financing, capital needs and timelines. Dawn describes the extended review period as running through early 2027, so the end date is not consistently reported. First production was originally targeted for the end of 2028. Barrick has not formally confirmed a new date, and it has cautioned that previously disclosed costs and schedules could change.
Estimates of the cost of delay vary. Dawn has reported a private-sector source as saying costs could rise by $8 billion to $10 billion even if work resumes within a year. Dawn has also reported an insider with ties to the company as saying delays might raise costs by 10 per cent at most. The $8 billion to $10 billion figure is attributed to the Dawn source, not to the ICMA.
Earlier government figures were also higher than some of these estimates. Express Tribune reporting has cited a 2025 Economic Coordination Committee decision on Phase I of $7.72 billion, including $5.8 billion in capital expenditure. This is a different measure from the ICMA's $7 billion total, and it is not clear how the two figures relate.
Long-term potential
According to ProPakistani's account, the report estimates the project could generate about $74 billion in free cash flow over its life, with peak construction employment of 7,500 and about 4,000 permanent jobs. It cautions that this cash flow is not revenue directly accruing to Pakistan. Actual benefits will depend on ownership distributions, taxes, royalties, reinvestment and local business participation.
Reko Diq is designed to produce copper and gold concentrate. Smelting and refining are outside its current scope, so domestic value addition is not guaranteed. The report, as relayed, calls for transparent disclosure of capital commitments, independent oversight and regular financial and operational assessments, so that the project does not become a burden on public enterprises.
Sources
- Pakistan's Reko Diq Project Faces $2.1 Billion Cost Hike: Report — ProPakistani, 17 November 2026
- Reko Diq cost increase raises questions over returns for state-owned firms — Minute Mirror, unknown
- Reko Diq costs reach USD 9.1 billion, ICMA flags risks — Nukta, unknown
- Reko Diq project may face further delay — Dawn, unknown