Pakistan plans smart meters for 16.2 million consumers in five DISCOs
The plan relies on private investment and payments through bills, but reports differ on total cost and on whether consumers would pay upfront or over 12 years.
Key points
- Pakistan plans to replace 16.219 million conventional meters with smart meters across LESCO, MEPCO, PESCO, HAZECO and QESCO, according to TechJuice.
- IFC estimates $60 to $80 per meter, which TechJuice says puts total investment at roughly $973 million to $1.298 billion.
- TechJuice, ProPakistani and Bloom Pakistan describe no upfront charge, but Business Recorder, as cited by Profit, says consumers would repay costs through bills over 12 years.
- The Federation of Pakistan Chambers of Commerce and Industry (FPCCI) has urged the Private Power and Infrastructure Board (PPIB) to suspend the framework until costs are independently assessed.
Pakistan is planning to replace 16.219 million conventional electricity meters with smart meters in five power distribution companies, according to TechJuice. The project would be financed through private investment under a proposed public-private partnership. TechJuice puts the estimated investment at up to $1.3 billion.
Scope and cost
The five DISCOs covered are LESCO, MEPCO, PESCO, HAZECO and QESCO. Implementation would be in phases, with priority feeders targeted first, TechJuice reported.
The International Finance Corporation (IFC) estimates the cost at $60 to $80 per meter. On that basis, TechJuice says total investment would be about $973 million to $1.298 billion.
How it would be paid for
Under the proposed model, private investors would receive an agreed payment per meter through monthly electricity bills, in local currency. On that basis, consumers would pay nothing upfront for installation, according to TechJuice, ProPakistani and Bloom Pakistan.
That framing is disputed. Business Recorder, as carried by Profit, reports that consumers would repay installation costs through their bills over 12 years.
Competing figures and objections
Business Recorder, as cited by Profit and Energy Update, gives a much higher total of $2.3 billion for the smart meter project. The available material does not explain the gap between that figure and the $1.3 billion estimate.
The FPCCI has estimated that consumers could end up paying about Rs1.4 trillion over 12 years, according to Profit. It has urged PPIB to suspend the framework until costs are independently assessed.
Process and next steps
IFC has been appointed transaction advisor to develop the financial, technical and legal framework, TechJuice said. IFC is due to discuss the project and wider power sector reforms with the Power Division during a visit from 24 November to 2 December.
Energy Update reported that PPIB held a stakeholder consultation chaired by its acting managing director, with an IFC representative joining online. According to Energy Update's report, a pilot is expected next month, with more consultations planned in Karachi, Lahore and Islamabad. TechJuice mentioned market consultations in Karachi and Islamabad to gauge investor interest.
TechJuice says the rollout is expected to finish within two years. The other reports do not mention that timeline.
Why it matters
The programme aims to cut distribution losses, improve billing accuracy and revenue recovery, strengthen grid reliability and curb electricity theft, according to TechJuice. No official PPIB, Power Division or NEPRA notification confirming the 16.2 million figure or the no-upfront-cost arrangement was identified in the material reviewed. The plan remains a proposal.
Sources
- Pakistan Plans Free Smart Meters for 16.2 Million Consumers — TechJuice, 21 November 2026
- IFC to Take Up $1bn Smart Metering Project with Power Division — Bloom Pakistan, 21 November 2026
- Pakistan Plans 16.2 Million Free Smart Meters Rollout — ProPakistani, 21 November 2026
- PPIB Plans $2.3bn Smart Meter Project, FPCCI Warns of Rs1.4trn Consumer Burden — Energy Update, 21 November 2026
- Pakistan's $2.3 billion smart meter plan faces objections — Profit by Pakistan Today, 21 October 2026