Peshawar Northern Bypass to open within two months, says Aleem Khan

The communications minister said the road, stalled for 18 years, should be operational in two months, with Rs5 billion reported from the NHA's own resources for the funding gap.

Key points

  • Communications Minister Abdul Aleem Khan said the Peshawar Northern Bypass should be operational within two months.
  • According to TechJuice, he announced Rs5 billion from the National Highway Authority's own resources to cover a funding shortfall.
  • TechJuice reported that remaining underpasses, flyovers and link roads are being built on an emergency basis.
  • In October, NHA progress details cited by The Nation gave 31 January 2027 as the completion date.

Federal Communications Minister Abdul Aleem Khan has directed that the Peshawar Northern Bypass be completed within the next two months. He gave the instruction during a visit to the project site in Peshawar, according to Radio Pakistan.

TechJuice reported that the bypass has remained incomplete for 18 years and is expected to become operational within the next two months. It said the minister made the remarks during a site visit on Thursday.

Rs5 billion for the funding gap

According to TechJuice, the minister announced that Rs5 billion had been allocated from the National Highway Authority's (NHA) own resources to address the project's funding shortfall and speed up construction. The Nation, in a report dated 20 November 2026, was also cited as saying the NHA had released the amount and was confident the project would be finished within two months. We could not view the full text of that report, so this account relies on summaries of it.

Remaining work

TechJuice said the remaining underpasses, flyovers and link roads were being completed on an emergency basis to meet the revised deadline. Once open, the bypass is expected to ease traffic, help commercial activity and give relief to residents of Peshawar and nearby districts, the outlet said.

According to a summary of The Nation's report, the prime minister would inaugurate the bypass after its completion.

Earlier schedule

An earlier report by The Nation, dated 24 October 2026, cited NHA progress details that gave 31 January 2027 as the completion date. By that summary, construction of Package-I was fully complete, Package-II stood at 79 percent and Package-III-A at 82 percent.

No source says how the new two-month target relates to the January date, or whether the schedule has changed. Reports also differ on how long the project has been stalled: most say 18 years, while NewKerala says 17.

Sources

  1. Aleem Khan directs completion of Peshawar Northern Bypass within two months — Radio Pakistan, 19 November 2026
  2. Peshawar Northern Bypass to Be Completed Within Two Months — TechJuice, 20 November 2026
  3. Rs5 billion released for Peshawar Northern Bypass completion — The Nation, 20 November 2026
  4. Peshawar Northern Bypass project to be completed by January 31 — The Nation, 24 October 2026
  5. Pakistan Delays Peshawar Northern Bypass Project for 17 Years — NewKerala, unknown

How this story was made

Researched and written by the Pakistan Republic AI newsroom from the sources listed above, then checked against them before publishing. Stories about people, politics, courts or crime are also reviewed by an editor.

Report an error · How we use AI

More from Pakistan