Rock collapse at Tarbela T-5 site sends water into tunnel; no casualties, says Wapda
Wapda says the main tunnel and powerhouse are undamaged, while Swabi officials urge people to stay out of the Indus as extra water is released from the dam.
Key points
- A weak rock mass collapsed at the Tarbela Dam 5th Extension Project site on Monday, letting water into a tunnel and the under-construction powerhouse area, Wapda said.
- Wapda said all workers were evacuated and no injuries or deaths were reported; work was suspended and an emergency declared.
- Wapda said the Intake Pit has been drained, dewatering of the powerhouse has begun, and the main tunnel, powerhouse, tailrace culvert and switchyard were not damaged, though the Haripur deputy commissioner said damage was still being assessed.
- The Swabi deputy commissioner said extra water released from Tarbela could raise the Indus River level and asked people to avoid bathing, swimming and boating.
A rock mass collapsed at the Tarbela Dam 5th Extension Project (T-5) construction site on Monday, sending water into nearby work areas, the Water and Power Development Authority (Wapda) said. An emergency was declared, construction was suspended and workers were moved to safer areas. No loss of life was reported.
What Wapda says happened
According to Wapda, weak rock gave way during excavation of the 2nd Bench Connecting Tunnel. This allowed water from the Intake Pit to enter the tunnel and the under-construction powerhouse area.
The authority said all workers were evacuated safely. It said the Intake Pit had been fully drained and no more water was entering the downstream work sites. Dewatering of the powerhouse has started.
Wapda also dismissed reports that the T-5 tunnel had collapsed. It said the main tunnel, the powerhouse under construction, the tailrace culvert and the switchyard had not been damaged. Senior Wapda officers, the project engineer and the contractor were assessing the situation.
Damage assessment
The accounts differ in tone on damage. Haripur Deputy Commissioner Waseem Ahmed, quoting project officials, said authorities were still assessing whether the tunnel, powerhouse and other structures in the working area had sustained damage. Wapda, in its statement, said the main structures it listed were not damaged. The extent of any damage has not been independently confirmed.
Warning along the Indus
A senior district administration official said there is currently no threat of flooding or inundation downstream of Tarbela. Separately, Swabi Deputy Commissioner Nasarullah Khan said additional water had been released from the dam for "unavoidable" reasons. He said this was expected to raise the flow and level of the Indus River.
He asked citizens to avoid bathing, swimming and boating in the river, to follow public safety notices, to ignore rumours and to rely on the official page for information.
Cause described differently
Wapda attributes the incident to the collapse of weak rock during excavation. The headline of an Express Tribune report, however, refers to a protective bund breach and says work was suspended indefinitely. The full text of that report was not available, so the details behind that description could not be checked.
Background
In July, a government-constituted inquiry committee held the contractor, the consultant and Wapda responsible for an earlier cofferdam collapse at the 1,530MW project. It cited unauthorised design changes made after the contract was signed as one of the main reasons.
That collapse contributed to a delay of at least two years and a cost rise of more than 285 per cent, from Rs82 billion to Rs317 billion, according to Dawn. Completion had been scheduled for the end of June 2028, instead of 2026, before Monday's incident.
The World Bank and the Asian Infrastructure Investment Bank are providing $390 million and $300 million respectively. Once finished, the project would lift Tarbela's installed capacity from 4,888MW to 6,418MW.
Sources
- Water surges into downstream work areas after rock mass collapse at Tarbela Dam — Dawn, 2026-11-09
- Tarbela T-5 project work suspended indefinitely after protective bund breach — Express Tribune, 2026-11-09
How this story was made
Researched and written by the Pakistan Republic AI newsroom from the sources listed above, then checked against them before publishing. Stories about people, politics, courts or crime are also reviewed by an editor.