Tarbela T-5 work suspended after bund breach floods tunnel

WAPDA says all workers are safe and the main tunnel and powerhouse are undamaged, while Haripur's deputy commissioner says an investigation into the breach has been launched.

Key points

  • Work on the Tarbela 5th Extension Hydropower Project has been suspended indefinitely after water flooded Tunnel Five, according to Haripur Deputy Commissioner Waseem Ahmed.
  • WAPDA said all workers were evacuated safely and no casualties were reported; Ahmed said one worker who was swept away was rescued by emergency teams.
  • WAPDA rejected reports of a tunnel collapse and said the main tunnel, powerhouse, tailrace culvert and switchyard were not damaged.
  • The accounts of the cause differ: the deputy commissioner cited a protective bund breach, while WAPDA cited a weak rock collapse. A high-level inquiry will examine the failure.

Construction at the Tarbela 5th Extension Hydropower Project has been suspended indefinitely after water flooded Tunnel Five on Monday, according to The Express Tribune. Haripur Deputy Commissioner Waseem Ahmed said the water entered after a protective bund gave way. The Water and Power Development Authority (WAPDA) said a weak rock mass collapsed during excavation. All workers were evacuated and no casualties were reported.

What WAPDA said

WAPDA said the rock collapse happened during excavation of the 2nd Bench Connecting Tunnel. This let water from the Intake Pit enter the tunnel and the powerhouse area.

WAPDA said the Intake Pit water has been completely drained and no more water is reaching downstream work sites. Dewatering of the under-construction powerhouse has begun. Senior officers, the engineer and the contractor are assessing the situation.

The authority also rejected reports that the tunnel had collapsed. It said there was no damage to the main tunnel, the powerhouse, the tailrace culvert or the switchyard.

Inquiry under way

Ahmed visited the site and confirmed that water entered the tunnel after the protective bund gave way. He said the administration and rescue agencies moved all Pakistani and foreign workers to a safe place.

One Pakistani worker was swept into the water as the tunnel flooded, but emergency teams rescued him, Ahmed said. He said work on the project has been suspended indefinitely and an investigation has been launched. A high-level inquiry will examine whether a structural weakness or technical fault caused the bund to fail. He said the next steps would be decided after the investigation report.

Differing accounts of the cause

The two accounts of what caused the flooding differ. The deputy commissioner described the failure of a protective bund. WAPDA's statement described a rock collapse during tunnel excavation. The inquiry is expected to examine the circumstances.

About the project

The project is being built at Tunnel No. 5 of Tarbela Dam. It is meant to add 1,530 megawatts through three units of 510MW each, raising the dam's installed capacity from 4,888MW to 6,418MW. It was expected to generate an average of 1.347 billion units of electricity a year.

WAPDA awarded the $354.6 million civil works contract to Power Construction Corporation of China Limited in May 2021. The approved project cost is $807 million. The World Bank is providing $390 million and the Asian Infrastructure Investment Bank $300 million.

History of delays

The project has faced repeated delays. According to The Express Tribune, its completion deadline has moved from the original five-year schedule to September 2027. In September 2024, a project director told a Senate committee that delays were caused partly by difficulty obtaining a no-objection certificate from the Indus River System Authority for closing Tunnel 5.

Work was also suspended temporarily in August 2025, when rising reservoir levels and higher inflows sent water into the construction site.

Sources

  1. Tarbela T-5 project work suspended indefinitely after protective bund breach — The Express Tribune, 2026-11-09